Sample snagging report · Published in full

The report is where we start, not where we stop

Every defect is written up with the measurement we took and the deviation normally accepted for it. We measure the way a UK housebuilder is measured, by people who spent twenty years working to NHBC standards, BS 5606 and BS 5385. This is the same document our clients receive, with the property and owner removed.

British-founded practiceReport delivered immediately on site20 years UK construction experienceWorking in all 7 Emirates★★★★★ 5.0 on Google

What is in it

What a snagging report contains: six parts, in this order

The structure does not change between properties. A villa report is longer than an apartment report; it is not different.

01

Cover and summary

The property, the date, who attended, how long we were on site, and the defect count broken down by severity. One page.

02

The defect schedule

Every defect, numbered and located to the room and the element. Photographed. Measured where a measurement applies.

03

The acceptable deviation

Set beside each reading, so a developer can see how far out the work is. This is the part that turns an opinion into a claim.

04

Photographic record

Wide shot for location, close shot for the defect, and the instrument in frame where a reading was taken.

05

Re-inspection status

Each item carries its own state: open, disputed, or closed with the date we verified the repair.

06

Developer-ready export

The same schedule as a plain list your developer can work from, without our commentary.

A page from the schedule

An example snagging defect entry

Two entries, reproduced as they appear in the report. The measurement, the acceptable deviation and the action are all on the same line as the photograph.

D-041majorMaster bedroom · Window 2

Window frame out of plumb; seal compromised at head

Measured
8mm out of plumb over 2m
Acceptable deviation
3mm per metre

Required actionRe-set frame, replace head seal, re-test.

Photo D-041D-041
D-042moderateKitchen · Floor tiling, bay 3

Hollow-sounding floor tiles

Measured
6 of 40 tiles hollow (15%), two at the doorway
Acceptable deviation
Up to 5%, none at doorways

Required actionHollow tiles to be lifted and rebedded. Re-inspect on completion.

Photo D-042D-042

Illustrative entries prepared for this page. They are not findings from a client's property.

A hand resting on a tiled floor beside a steel straightedge in a bright room
LengthAn apartment runs to forty pages. A villa, rather more

The full document

Request the full sample report

The complete sample report, unredacted apart from the address and the owner's name. No form-filling beyond an email address.

Request the sample report →

Before the keys change hands

Tell us the property and the date. A fixed fee comes back the same working day.

Over 7,000 sq ft, or not sure which service? Request a fixed fee.