Crack at window reveal has opened since handover
- Measured
- 1.4mm wide, 620mm long
- Acceptable deviation
- Serviceability limit 0.5mm
Required actionCut out, reinforce and make good; monitor for further movement.
The last month you can still make it the developer's problem
This is your final chance to find hidden defects before your developer's obligation to fix them ends, while you still have the right to claim. We inspect what a year in the property has exposed, measure each failure, and give you a claim-ready report the developer cannot wave away.
In plain terms
When you take handover, your developer must fix defects at no cost to you for a set period, usually around twelve months. That period is the warranty, also called the defect liability period. An 11-month warranty inspection is a full inspection carried out in its final weeks, so that anything hidden, or anything that has appeared since you moved in, is found and put in writing while you can still claim.
The warranty
For roughly twelve months after handover, the developer must put right defects in your property at its own cost. Your sale and purchase agreement sets the exact period and what it covers.
The inspection
A full inspection in month ten or eleven: every system re-tested, thermal imaging, moisture readings and a borescope for hidden spaces, plus a line-by-line check of your original snagging list.
The deadline
Once the period closes, the cost of putting defects right is usually yours. This is your final chance to find hidden defects and claim for them while the developer is still obliged to fix them.
What a year in the property reveals
A handover inspection catches what was built wrong. This one catches what has moved, failed or reopened since, while the developer is still the one who has to put it right.
01
Cracking and settlement
A year of movement opens what was invisible at handover. We record width, length and location so a structural crack is not dismissed as shrinkage.
02
Waterproofing and leaks
Wet areas, balconies and the ceilings below bathrooms, after the property has been through a rain season and a full summer of use.
03
Grout, silicone and seals
Failed joints around baths, basins, shower trays and window heads, which is where water gets into the structure first.
04
Doors and windows out of alignment
Frames that have moved, doors binding on their jambs, sliding runs dropping, seals no longer meeting.
05
Water pressure and drainage
Flow at every outlet, standing water at floor gullies, slow drainage and trap seals that have dried out or were never right.
06
Electrical faults surfaced in use
Circuits that trip, sockets that were never live, distribution boards mislabelled against what they actually control.
07
Snags the developer already closed
We check your original list item by item. Work signed off as complete at handover is reopened if it does not hold.

Check how long your warranty has left
Pick a date and see your fixed fee in about a minute. Nothing to pay today.
How we measure
Eleven months in, a developer's first instinct is to call a defect wear and tear. A measurement closes that argument off. Every entry records the reading, the acceptable deviation where one is recognised, and the clause of your own contract it falls under.
Each entry is graded critical, major, moderate or minor, so the items that must be closed before the period expires are unmistakable.
How it works
We work back from it and book you into month ten, leaving time for the repairs.
Around half a day. We work around a tenant, and you need not attend.
Before we leave the property, each defect cited against the clause it falls under.
You submit it with our wording. On Complete, we then re-inspect what they say they fixed.

What's in your warranty report
Fewer entries than a handover report, and harder ones. Each defect located, photographed, measured, graded, and cited against both the published standard and the defects clause of your own sale agreement.
Crack at window reveal has opened since handover
Required actionCut out, reinforce and make good; monitor for further movement.
Moisture reading below shower; waterproofing failed in service
Required actionExpose, re-waterproof the tray junction, make good ceiling. Reopened from snag D-088, closed at handover.
Book your inspection before the warranty closes
Fixed fee shown up front. Nothing to pay today. Your report on site before we leave.
Submitting the claim
A claim submitted on the last day of the period is a claim with no time left for the repairs. We work to close items inside the window, not merely to lodge them inside it.
The report is already in the developer's own format, with the measurements and clause references attached, ready for you to send.
We check the work rather than take the word for it, and reopen anything that has not held. Signed off by us, or it is not closed.
Whatever the developer refuses or leaves undone is recorded with our measurements, dated, so you hold the evidence if you take it further. How the period works →
Where we work
After a few hundred units in the same development you stop looking for defects at random. We know which towers crack at the reveals in year one and which wet areas start leaking after a summer of use.
All communities →★★★★★
“Very thorough and professional. I'll be using them from now on. Thanks for the great service!”
Google review
★★★★★
“Great communication throughout. The report was excellent. Thanks again”
Google review
★★★★★
“Great service”
Google review
Still deciding?
Booking reserves your slot and nothing is paid today. Prefer to talk first? Message us on WhatsApp.
It is a full inspection carried out in the last weeks of your developer's warranty, usually around month eleven. Its job is to find defects that were hidden at handover or have appeared since you moved in, and to put them in a report you can submit while the developer is still obliged to fix them at its own cost. Once the period closes, that obligation usually ends.
Most developer contracts set the defect liability period at around twelve months from handover for general finishes, sometimes with a longer period for structural items. The exact length and scope are in your sale and purchase agreement, so check the clause for your own development.
We record anything structural we can see, such as cracking, with its width, length and location. Structural liability is dealt with separately from the general warranty and generally runs longer, so where something looks structural we say so in the report and tell you who to instruct.
Instruct us in month ten. That leaves time for us to inspect, for the developer to carry out the repairs, and for us to go back and check them before the liability period closes. Leave it to the final fortnight and you may run out of window for the repairs themselves, even if the claim is submitted in time.
Then the developer's obligation to correct defects at no cost has usually ended with it, and anything outstanding becomes yours to pay for. It is still worth an inspection if you are about to spend money on repairs, because you will at least know the full extent of what needs doing before you commission work.
Yes, and a good number of these instructions come from owners who used someone else, or no one, first time. We inspect from scratch against the same standards. If you have an earlier report from another firm, send it and we will check those items too.
No. We work around the tenancy, and we need roughly half a day of access. Defects that are the developer's responsibility remain so whether or not the property is occupied, though we distinguish clearly in the report between construction defects and ordinary occupancy wear, so nothing is claimed that should not be.
You submit it yourself, and we make that straightforward. The report is in the developer's format, with our measurements and clause references attached, and we show you how and where to send it. On Complete, we also come back and re-inspect the repairs once the developer says they are done.
No. We attend under your authority letter or power of attorney, inspect, and send the report the same way. Most of these instructions are handled entirely remotely.
It is a fixed fee based on the size of the property, quoted before we attend. If you instructed us on Complete, we diarised the check at handover and will remind you before the period closes. Ask us and the fee comes back the same working day.
The property has now been lived in for a year. A handover inspection catches what was built wrong; this one also catches what has since moved, cracked, leaked or failed under use, and it re-tests anything the developer previously closed off. It is the same discipline applied to a building that has been through a full Dubai summer.
Before the warranty closes
Tell us when you took handover. We will work back from it, tell you how long you have left, and come back the same working day with a fee and a date.
Over 7,000 sq ft, or not sure which service? Request a fixed fee.